Official opening | December 2010 |
---|---|
Total floors | 28 stories + 1 basement |
Construction | Reinforced concrete core wall and floors with pre-stressed beams, compliance with Indonesian Seismic Design Code for Buildings 2002. Tempered glass curtain wall + safety film at ground and mezzanine floor. Granite cladding on ground and mezzanine floor pillars and beams. Raised floor provided on typical floors. |
Power Supply | 4,150 kVA main electricity supply 4,000 kVA building electrical load assumption |
Back-up Power | 100 % back-up capacity using 2 x 2,000 kVA Mitsubishi generators |
Air Conditioning | Central water cooling system 24 hours chilled water available for server room |
Lighting | 500 lux illumination on typical floors |
Telecommunication | Vertical shaft for fiber optic and standard cable |
Lift |
14 Passenger Lifts Low Zone, GF – 16/F High Zone, 16/F – 28/F 1 Service Lift, Basement – 28/F 2 Lifts, 750 kg load capacity |
Fire & Safety | Heat and smoke detector alarms, automatic fire alarm, fire hydrant and fire extinguishers, sprinkler system, emergency lighting, exit signs, public address system, 2 fire stairs with double handrails, emergency lighting and pressurized fresh air. |
Executive Toilet | Available per floor, 3/F – 28/F, with shower cubical and hot water |
Public Toilet | Available per floor, GF – 28/F |
Pantry & Ablution | Available per floor, 2/F (mezzanine floor) – 28/F |
Prayer Room | Available at Basement level |
Car Parking | Available in car park building, 2, 7 floors, approximately 800 lots and Plaza Senayan’s car park building. |
Sentral Senayan III | |
Developer & Manager | PT Senayan Trikarya Sempana |
Main Contractor | PT Kajima Indonesia |
Design architects & Engineers | Kajima Design, Japan Kajima Design Asia, Singapore |
Project Architects | PT Anggara Architeam |
Structural Engineers | PT Wiratman & Associates |
M/E Engineers | PT Sigmatech Tatakarsa |